Construction Continues on Clearfield County Bridge Project - Greenwood Township

See below for more information on the Rapid Bridge Replacement Project

  • Who Is Walsh Group, Plenary Group, Granite & HDR?
  • What Is The Rapid Bridge Replacement Project?


June 20, 2016

The Pennsylvania Department of Transportation’s (PennDOT) Rapid Bridge Replacement Project continues in Clearfield County with reconstruction set to begin the week of June 27 for the following bridge:
                        
Route 219 over Curry Run in Greenwood Township (JV38). Signals are in place to control an alternating traffic pattern. Replacing this bridge will allow PennDOT to remove it from Clearfield County’s structurally deficient list. The 50 foot bridge dates from 1925 and carries and average of more than 2,400 vehicles each day. Completion of the new bridge is expected by November.

Construction starts are subject to change due to weather, equipment or other unforeseen issues. 

facebook Email Twitter YouTube 511pa

About The ProjectContact Us

4 Penn Center Blvd., Suite 100
Pittsburgh, PA 15275

info@parapidbridges.com

Hotline: 877-444-9990
Hours: M–F from 8:30 a.m. – 5 p.m. ET

Contact:  Andrew Dressler,  312.756.9119

Plenary Walsh Keystone Partners believes in engaging local community and disadvantaged business enterprise (DBE) resources to benefit our projects and the communities in which we do business. We seek to establish relationships with local DBE firms, encourage and assist potential DBEs to obtain necessary certification and prequalification, and aid development of DBEs through their active involvement.

View Available Jobs    An Equal Opportunity Employer, Disability/Veteran.

Copyright © 2019 Plenary Group | Walsh Group | Granite | HDR. All rights reserved.

Plenary GroupWalsh GroupGraniteHDR