June 27, 2018
Construction for the Bentleyville Road (Route 2023) bridge, spanning Pigeon Creek in Fallowfield Township, Washington County, has been postponed. It was previously scheduled to begin during the week of June 25.
Construction is now expected to begin during the week of July 16 and be complete in mid-December. During this time, an alternating traffic pattern will be controlled by temporary traffic signals.
In the event of unfavorable weather or unforeseen activities, this schedule may change.
This bridge is referred to as JV-530 and is one out of the 558 bridges being replaced under the Rapid Bridge Replacement Project. JV references the joint-venture partnership between Walsh/Granite, which is leading construction for the entire project.