September 25, 2017
Construction for the Morrow Road (Route 3008) bridge, spanning McLaughlin Run in Upper St. Clair Township, Allegheny County, is scheduled to begin as part of the Pennsylvania Department of Transportation’s (PennDOT) Rapid Bridge Replacement Project.
Replacement of this bridge will allow PennDOT to remove it from Allegheny County’s structurally deficient bridge list.
Construction is expected to begin during the week of October 9 and be complete in mid-November. During construction, drivers will be directed to follow a detour along McLaughlin Road (Route 3004), Lesnett Road (Route 3034) and Mayview Road (Route 3005).
In the event of unfavorable weather or unforeseen activities, this schedule may change.
This bridge is referred to as JV-437 and is one out of the 558 bridges being replaced under the Rapid Bridge Replacement Project. JV references the joint-venture partnership between Walsh/Granite, which is leading construction for the entire project.